Construction Law Newsletter – Amendment to Notice of Defect Claim

The process of resolving a construction or design defect claim in Florida starts with the claimant providing notice of the claims to the responsible parties.  In some instances, the notice of the claim lacks specificity.  Thus, the recipients of the notice are left wondering about the nature and location of the alleged defect, as well…

Notice to Owner and Common Ownership

“Marble Unlimited, Inc. v. Weston Real Estate Investment Corporation, 38 Fla. L. Weekly D686b, Case No. 4D11-3113, issued March 27, 2013: Dismissal of contractor’s foreclosure of construction lien for failure to served a notice to owner was reversed due to the common identity of the corporate owner (following a transfer of title from one related…